South Star Battery Metals announces filing of Technical Report with significant increase in mineral resources and positive BamaStar economic results for vertically integrated graphite mine and value-add project in Alabama.
Arizona Sonoran announces that following a request for proposal, they have appointed M3 Engineering, Tucson, to lead the Cactus Project Pre-Feasibility Study and to act as metallurgical program lead. The consultants will include AGP Mining (mining), Clear Creek (hydrology), ALS Geotechnical (geology), and Partners in Performance (real-time modeling and optimization), all of whom have contributed to ASCU’s prior studies.
Liberty Gold is pleased to announce the results of a Preliminary Feasibility Study at its flagship Black Pine Oxide Gold Project in southern Idaho, USA completed in part by AGP Mining Consultants Inc.
Discovery Silver announces financial results for the three months, and six months ended June 30, 2024. The company also provided a summary of key events in 2024 related to Discovery’s 100%-owned Cordero silver project in Chihuahua State, Mexico including the release of the Cordero Feasibility Study results in February and subsequent filing of the technical report completed in part by AGP Mining Consultants.
Arizona Sonoran reports results from an NI 43-101 Preliminary Economic Assessment on its 100%-owned Brownfield Cactus Project in Arizona and was completed in part by AGP Mining Consultants.
Troilus Gold has filed its NI 43-101 Technical Report for the Troilus Project’s Feasibility Study. The FS, prepared by AGP Mining, is in accordance with the NI 43-101 Standards of Disclosure for Mineral Projects. The report supports disclosures made in the company’s May 14, 2024, news release and is available on the Troilus website and SEDAR.
Sierra Metals announces that it has filed technical reports in respect of its previously announced updated Mineral Resource and Reserve Estimates for each of the Yauricocha Mine in Peru and the Bolivar Mine in Mexico. The Technical Reports were prepared by AGP Mining Consultants and there are no material differences in the reports from those disclosed in the Company’s press release.
Alta Copper is pleased to announce it has filed an NI 43-101 Technical Report & Preliminary Economic Assessment for its 1005 owned Cañariaco Copper Project. The PEA was prepared by AGP Mining Consultants, Ausenco Engineering Canada, and Whittle Consulting.
Alta Copper is pleased to announce attractive economics results from the 2024 Optimized Preliminary Economic Assessment at its 100% owned Cañariaco Project , a world class porphyry copper project, located 700 km northwest of Lima. The 2024 PEA has been prepared by AGP Mining Consultants, Ausenco Engineering Canada, and Whittle Consulting Pty. Ltd., leading international engineering and mining consultancy firms.
Troilus Gold reports results from a Feasibility Study completed on the gold-copper Troilus Project and is prepared by AGP Mining Consultants in conjunction with Lycopodium and WSP.
Sierra Metals is pleased to announce the updated results for its NI 43-101 compliant Mineral Resource and Reserve Estimate for its Bolivar Mine with the report being prepared by AGP Mining Consultants.
Sierra Metals is pleased to announce the updated results for its NI 43-101 compliant Mineral Resource and Reserve Estimate for its Yauricocha Mine with the report being prepared by AGP Mining Consultants.
Mayfair Gold has approved advancing the 100% controlled Fenn-Gib gold project in the Timmins region of Ontario to the pre-feasibility study phase. Mayfair has hired AGP Mining Consultants to serve as the lead engineers of a multidisciplinary team.
Discovery Silver announced today the filing of the NI 43-101 Technical Report entitled “Cordero Silver Project, Technical Report & Feasibility Study” in respect of Discovery’s Cordero deposit in Mexico which was partially authored by AGP Mining Consultants Inc.
Panoro Minerals is pleased to announce the filing of the NI 43-101 Technical Report for the updated Mineral Resource Statement for the 100% owned Cotabambas Project in Peru, authored by AGP Mining Consultants Inc.
Nickel Creek Platinum Corp. is pleased to announce that further to its news release dated August 24, 2023 the Company has filed a Technical Report titled “Nickel Shäw Ni-Cu-PGM Project PreFeasibility Study for the Nickel Shäw Ni-Cu-PGM Project in Yukon, Canada
Lundin Mining is pleased to announce the closing of the acquisition of fifty-one percent of the issued and outstanding equity of SCM Minera Lumina Copper Chile. A technical report for the Caserones mine, prepared by AGP Mining Consultants, was filed today in accordance with NI 43-101 Standards of Disclosure for Mineral Projects and is available for review on SEDAR.
Discovery Silver is pleased to announce it has filed its NI 43-101 technical report titled “Cordero Silver Project – NI 43-101 Technical Report & Pre-Feasibility Study” on SEDAR in respect of Discovery’s Cordero deposit in Mexico. AGP Mining Consultants supported Ausenco Engineering Canada, Hard Rock Consulting, and Knight Piésold in authoring the report.
Skeena Resources is pleased to announce the results of the Feasibility Study (FS) for the Eskay Creek gold-silver project located in the Golden Triangle of British Columbia. The FS for Eskay Creek was completed by Ausenco who were supported by AGP Mining Consultants and SRK Consulting (Canada). The study confirms robust economics for a conventional open-pit mining and milling operation, with low initial capital cost intensity and a high rate of return.
Magna Mining is pleased to announce it has filed on SEDAR an independent Feasibility Study Technical Report in respect of its Shakespeare Nickel Project in Ontario Canada which was prepared by AGP Mining Consultants.
Flying Nickel is pleased to announce it has commenced a drilling program at its 100% owned Minago nickel sulphide project in the Thompson Nickel Belt in Manitoba Canada where AGP Mining Consultants provided pit optimization and associated services.
Candente announces the Cañariaco Norte Mineral Resource Estimate (previously reported on Nov 1, 2010) has been updated by AGP Mining Consultants and DKT Geosolutions. The 0.15% Cu applied cut-off represents an approximate breakeven cut-off, based on parameters developed during the nearly completed 2022 Canariaco Norte PEA study.
Tarachi Gold Corp. - Magistral Mill and Tailings Project
Durango Mexico
Tarachi is pleased to announce the results from its Preliminary Economic Assessment (PEA) for the Magistral Mill and Tailings Project in Durango, Mexico. The PEA is based upon an updated Mineral Resource Estimate, also included in the PEA report, completed by AGP Mining Consultants.
Discovery Silver is pleased to announce results from its Preliminary Economic Assessment (PEA) on its 100%-owned Cordero Silver project located in Chihuahua State, Mexico with a PEA team supported by AGP Mining Consultants Inc.
Equinox Gold announced updated Mineral Reserve and Mineral Resource estimates for the Mesquite gold mine in California, USA. The Mesquite Gold Mine measured and indicated mineral resources increased by 65% of contained gold (exclusive of Mineral Reserves) and Inferred Mineral Resources increased by 30% of contained gold.
Skeena Resources announced it has filed the independent NI 43-101 Prefeasibility Study (PFS) Technical Report for the Eskay Creek gold-silver project as per the news release dated July 22, 2021.
Discovery Silver announced the project study team for its Preliminary Economic Study (PEA) will be led by Ausenco who will continue to work with AGP Mining Consultants who has already completed preliminary pit optimization work to assist with drill targeting. Preliminary mine scheduling work has also been completed by AGP Mining to evaluate the impact on project economics of different mining rates, mill throughput rates and cut-off grade and stockpiling strategies. The objective of this work is to optimize the Net Present Value (“NPV”) and capital efficiency (ratio of initial capital expenditure to NPV).
Cerrado Gold announced completion of an independent NI 43-101 Technical Report for the Las Calandrias project in Santa Cruz Province, Argentina. The technical report was prepared by AGP Mining Consultants for the purposes of confirming and allowing Cerrado Gold to adopt the work done by previous owners.
First Mining announced they have filed an independent Pre-Feasibility Study (PFS) technical report, prepared by AGP Mining, for its Springpole Gold Project which supports a 30,000 tpd open pit mining operation over an 11.3 year mine life.
Treasury Metals announces the results from a Preliminary Economic Assessment (PEA) for the Company's Goliath Gold Complex which includes the Goliath, Goldlund, and Miller deposits along a prospective 65-kilometre trend in northwestern Ontario.
Cerrado Gold closes the acquisition of Minera Mariana Argentina S.A. acquisition adding the Las Calandrias project with 379,000 ounces of gold and 6 million ounces of silver (Indicated) and 42,000 ounces of gold and 401,000 ounces of silver (Inferred) directly adjacent to MDN's Escondido deposit on its northern border.
First Mining announces positive results of Pre-Feasibility Study (PFS) completed for its 100%-owned Springpole Gold Project located in northwestern Ontario. The PFS results support a 30,000 tonnes-per-day open pit mining operation over an 11.3 year mine life.
Troilus Gold reports it has filed the Technical Report supporting the Preliminary Economic Assessment for the Company’s 100%-owned Troilus Gold Project, located within the Frôtet-Evans Greenstone Belt of northern Quebec which was prepared by AGP Mining Consultants Inc.
Equinox Gold announced that exploration success during the first half of 2020 has significantly increased Mineral Reserves and Mineral Resources at their Mesquite Gold Mine in California, USA.
Troilus Gold announced the filing of a technical report for its 100% owned property in Quebec. The technical report, prepared by AGP Mining Consultants, supports the scientific and technical disclosure in the Updated Mineral Resource Estimate (see news release dated July 28, 2020).
Troilus Gold Corp. is pleased to provide an updated mineral resource estimate, to be completed by AGP Mining Consultants, for its 100% owned Troilus property located 170 km by road northeast of Chibougamau, Quebec, Canada.
Troilus Gold Corp.has provided an update on new field exploration underway and major technical milestones in addition to AGP Mining Consultants having been retained to execute the PEA which is approaching completeion.
Satori Resources Inc. has engaged AGP Mining Consultants to update the mine design work previously completed for Satori in 2015. AGP is a Mining, Geology, and Processing firm based out of Toronto that has worked on several advanced stage projects both within Canada and globally.
Eskay Creek Gold & Silver Project, British Columbia, Canada
Skeena Resources is to commence a Prefeasibility Study (PFS) on its Eskay Creek gold-silver project in the Golden Triangle of northwest British Columbia, Canada. As a result of the proven success with the team that developed the Preliminary Economic Assessment (PEA) for Eskay Creek, Skeena will once again partner with AGP Mining Consultants, Ausenco Engineering Canada, and SRK Consulting with a target completion date for the PFS of summer 2021.
Equinox Gold Corp. is pleased to announce a positive Preliminary Economic Assessment (PEA), completed by AGP Mining Consultants, for development of an underground mine at the 100% company owned Aurizona Gold Mine in Brazil.
Foran Mining Corporation is pleased to announce that further to its news release of March 2020, it has filed an NI 43-101 Technical Report, completed in part by AGP Mining Consultants, for their Pre-feasibility Study (PFS) for their 100% owned McIlvenna Bay project. The PFS demonstrates that McIlvenna Bay is poised to be the centre of operations for a new mining camp.
Foran Mining Corporation announces positive Pre-feasibility Study (PFS) results for their 100% owned McIlvenna Bay project. The PFS was completed in part by AGP Mining Consultants.
Look for AGP Mining Consultants at PDAC 2020 !! The following AGP team members will be attending, please contact agp@agpmining.com if you would like to schedule a meeting:
Andy Holloway - Principal Process Engineer,
Gordon Zurowski - Princiapl Mine Engineer,
Paul Daigle - Principal Geologist,
Freddy Bravo - Senior Mine Engineer and
Clement Yeung - Senior Mine Engineer
Maritime Resources Corp.– Hammerdown Project – Newfoundland & Labrador, Canada
Maritime Resources is pleased to announce robust economic results from a Preliminary Economic Assessment (PEA) completed in part by AGP Mining Consultants for the Hammerdown gold project.
Jay Melnyk, Prinicpal Mine Engineer at AGP Mining Consultants will be in attendance at Roundup 2020 – please email sandra.atkinson@agpmining.com if you would like to arrange a meeting.
Eskay Creek Gold & Silver Project, British Columbia, Canada
Skeena Resources is pleased to announce that it has filed on SEDAR the independent NI 43-101 Preliminary Economic Assessment Technical Report for the Eskay Creek Gold-Silver Project (“PEA”), located in the Golden Triangle of British Columbia.
Euro Sun Mining announces they have filed an NI43-101 compliant technical report for the Preliminary Economic Assessment (PEA) for the exploitation of the Colnic Open Pit. The PEA was completed by AGP Mining and is for the initial phase of development of its Rovina Valley project.
AGP Principals, Andy Holloway, Gordon Zurowski and Jay Melnyk will be in attendance at the PDAC Conference. Please contact the office if you are unable to connect with them, and we will ensure your communications are forwarded.
Project Update
Mesquite Gold
USA
Equinox Gold Corp. announces an updated mineral reserve and resource estimate for its Mesquite Gold Mine and the filing of a new technical report, prepared by AGP Mining. Equinox Gold is quoted as stating “We are pleased with the results of the Mesquite technical report and look forward to realizing on optimization and mine life extension opportunities at Mesquite.”
Osisko Metals is pleased to announce the maiden Mineral Resource Estimate, prepared by AGP Mining, for its 100% owned Eastern Bathurst Mining Camp Project incorporating both the Key Anacon Deposits and the Gilmour South Deposit, all located south of the city of Bathurst, New Brunswick.
We are pleased to announce Mr. Neil Lincoln, P.Eng. is the latest addition to the growing AGP Mining team. With over 24 years of technical and leadership experience as a Mineral Processing Engineer and Study Manager in engineering consulting and operations related to the mining industry, Neil is a great asset to AGP’s already highly experienced team of Engineers and Geologists.
Project Update
Filo del Sol
Argentina & Chile
Filo Mining announced the results of a positive Pre-Feasibility Study at its 100% owned Filo del Sol project located on the border of Region III, Chile and San Juan Province, Argentina. The PFS confirmed and improved the initial work at Filo del Sol and highlights the incredible potential of the project.
IAMGOLD announced positive results from a Feasibility Study (FS) for its Boto Gold project. The FS was completed by AGP Mining and the results outline an economically robust project with an anticipated low cost of production and long operating life. The FS demonstrates a significant economic and operational improvement compared to the Pre-feasibility Study (PFS) results announced in February of this year.
New Dimension reported the results of an updated Mineral Resource Estimate (MRE) for the Las Calandrias Gold-Silver Project in Santa Cruz Province, Argentina. The updated MRE, prepared by AGP Mining Consultants, provides a detailed evaluation of the mineral resource potential of the adjacent high-grade Morena vein/breccia system.
Project Update
Nickel Shäw
Yukon, Canada
Nickel Creek Platinum announced an update on the status of its Nickel Shäw Project located in the Yukon, Canada.
Ascendant Resources Inc. is pleased to announce it has acquired from TH Crestgate a 25% interest in Redcorp Lda, which holds an 85% interest in the Lagoa Salgada Project located within the prolific Iberian Pyrite Belt in Portugal. Crestgate recently contracted AGP Mining Consultants to complete an updated Technical Report defining a preliminary Indicated Mineral Resource Estimate of 5.84 million tonnes grading 8.88% ZnEq and an Inferred Mineral Resources of 2.01 million tonnes grading 7.82% ZnEq, at a 3.5% ZnEq cut-off grade, at the LS-1 deposit with an additional Inferred Mineral Resource of 2.22 million tonnes grading 4.80% ZnEq, at a 3.5% ZnEq cut-off grade, outlined at the LS-1 Central deposit.
Global Energy announces the completion of a NI43-101 Resource Report carried out by AGP Mining Consulting Inc. on the Werner Lake Cobalt Property around the historic underground workings at the “Old Mine Site”, now referred to as the Minesite Deposit and the West Cobalt Deposit.
Wellgreen Platinum has succeeded in achieving all the objectives it set out to accomplish through the Phase 1 metallurgical programme on its Wellgreen nickel/copper/platinum-group metals (PGMs) project, in Canada’s Yukon Territory. The company has engaged AGP Mining Consultants to work with the team on an internal review of mine planning.
Happy Creek Minerals has announced an update to its mineral resource estimate completed by AGP Mining Consultants in accordance to NI43-101 for the Ridley Creek zone, and a first-time resource for the BN zone on its 100% owned Fox tungsten property.
Project Update
Lac Knife Flake Graphite
Quebec, Canada
Focus Graphite reports a 26% increase in Measured and Indicated Mineral Resources at its Lac Knife Flake Graphite project in Quebec. The updated Mineral Resource Estimate is based on 231 drill holes totalling 22,505 metres of historic and recent drilling and was prepared by AGP Mining Consultants Inc.
Luna Gold has announced the results of its pre-feasibility study on it’s 100% owned Aurizona Gold Mine project located in north-eastern Brazil. The PFS, prepared by AGP Mining Consultants, indicates that the project represents a robust, rapid pay-back, high margin, simple open pit mining project that demonstrates strong returns in the current gold price environment.
Entree Gold files NI43-101 Technical Report for Ann Mason Project, Nevada. The 2015 PEA was completed independently by AGP Mining Consultants in conjunction with Amec Foster Wheeler and Porcupine Engineering Services (PES). The QP’s responsible for the report include AGP’s Gordon Zurowski, P. Eng, Jay Melnyk, P. Eng., Pierre Desautels, P. Geo and Lyn Jones, P. Eng., in addition to engineers and geologists from Amec Foster Wheeler and PES.
Alabama Graphite has engaged AGP to complete a Preliminary Economic Assessment (PEA) on their 100% owned Coosa Graphite Project in Alabama, USA. In addition, AGP has provided technical assistance with a selection of graphitic samples for a pilot plant program to be carried out at SGS Lakefield, Ontario.
Project Update
Ann Mason Project
Nevada, USA
Entrée Gold has announced that it has received the results of an updated Preliminary Economic Assessment, completed by AGP Mining Consultants, for its 100%-owned Ann Mason copper-molybdenum porphyry deposit in Nevada.
Project Update
Volta Grande
Pará, Brazil
Belo Sun has announced the completion and filing of a Feasibility Study completed on their 100% owned Volta Grande Project. The report contains positive results was completed by AGP Mining Consultants; it has been filed on SEDAR.
Project Update
Strieborna
Slovakia
Global Minerals is pleased to announce it has filed on SEDAR the Preliminary Economic Assessment (PEA) which was completed by AGP Mining Consultants for its 100% owned Strieborná silver-copper-antimony deposit in Slovakia.
Project Update
Werner Lake Cobalt
Ontario, Canada
Global Cobalt has engaged AGP to complete a resource model and NI43-101 report for the Werner Lake Cobalt project commencing immediately.
Project Update
Strieborna Project
Slovakia
Global Minerals releases positive results in the Preliminary Economic Assessment completed by AGP for the Strieborna Silver-Copper project in Slovakia.
Belo Sun has announced a Preliminary Economic Assessment completed by AGP Mining for a staged development approach based on the updated mineral resource for its 100% owned Volta Grande gold project in Para State, Brazil.
AGP Mining has been retained to work in conjunction with Met-Chem in the completion of a Feasibility Study of the Lac Knife deposit. AGP will provide the resource model along with assistance on the geology aspects of the Feasibility Study, including contribution to Met-Chem's NI43-101 report.
Project Update
Yaramoko Concession
Burkina Faso
Roxgold is pleased to announce the results of its Preliminary Economic Assessment (PEA) completed by AGP Mining Consultants, Toronto and prepared pursuant to NI43-101 for the 55 Zone on its 100% owned Yaramoko exploration permit in Burkina Faso.
Northern Graphite announces the economics in the previously released bankable Feasibility Study for the Bissett Creek project have been updated by AGP Mining Consultants to incorporate a new and larger resource estimate with some modifications to the capital and operating cost assumptions, and lower graphite prices.
Coastal Gold has been working on a number of initiatives following the successful merger with Ridgemont Iron Ore on June 28, 2013 and are moving ahead rapidly, working closely with AGP Mining Consultants to plan site work for the Preliminary Economic Assessment.
Project Update
Bissett Creek
Ontario, Canada
Northern Graphite recently announced a new resource estimate for the Bissett Creek graphite project which was prepared by AGP Mining Consultants Inc. and based on results from a recent 61 hole, 3,782 meter drill program. The drill program successfully achieved its objective of upgrading a significant portion of inferred resources to the measured and indicated categories.
Project Update
Yaramoko Concession
Burkina Faso
Roxgold was pleased to announce the SEDAR filing of a technical report prepared by AGP Mining Consultants titled “Resource Update Report for the Yaramoko, 55 Zone, West-Central Burkina Faso”. There are no material differences between the mineral resource estimate contained in Roxgold’ s March news release and the Technical Report filed this month.
Roxgold has announced an updated resource estimate for the 55 Zone deposit. The estimate was undertaken by AGP Mining Consultants and is based on 81,105 m of drilling and was prepared in accordance with NI43-101 standards.
Team Update
PDAC 2013
Toronto, Canada
AGP Principals, Andy Holloway, Gordon Zurowski and Pierre Desautels will be in attendance at the PDAC Conference. Please contact the office if you are unable to connect with them, and we will ensure your communications are forwarded.
Project Update
Piedras Verde
Sonora, Mexico
Frontera Copper, through its subsidiary Cobre del Mayo S.A. de C.V., has requested AGP Mining perform Strategic Mine Planning Studies at the Piedras Verde Mine in the state of Sonora, Mexico.
Project Update
Promontorio Project
Chihuahua, Mexico
AGP has been retained by Azure Minerals to estimate mineral resources at their Promontorio Cu-Au-Ag project located approximately 200 km west-southwest of the city of Chihuahua in the state of Chihuahua in Northern Mexico.
Project Update
Ann Mason Project
Nevada, USA
Entrée has filed a NI43-101 Technical Report entitled “Entrée Gold Inc., Preliminary Economic Assessment on the Ann Mason Project, Nevada, USA” The report was completed by AGP Mining Consultants and relates to the PEA and updated resource estimate for the Ann Mason copper-molybdenum porphyry deposit.
Project Update
Bissett Creek
Ontario, Canada
Northern Graphite has retained AGP Mining Consultants to update the current resource and reserve estimates, mine design and economic model once the new drilling results are available which is expected to be before year end. Additionally, AGP will review assay methodologies and procedures to investigate the fact that graphite production, based on calculated head assays from the locked cycle test program, was up to 12% higher than expected based on the initial assay grade of the samples.
Project Update
Yaramoko Concession
Burkina Faso
Roxgold has received the initial resource estimate from AGP Mining for the 55 Zone on its 100% owned Yaramoko Property.
Project Update
Bisha Mine
Eritrea
In conjunction with the work done by AGP Mining Consultants, Nevsun has recently announced new increased base metal Canadian NI43-101 compliant mineral resources and reserves estimates at its Bisha Mine in Eritrea. Expressed as contained metal, the copper reserves estimate is 6% higher and the zinc reserves estimate is 38% higher as of May 31, 2012, compared with the previous reserves estimate effective date January 1, 2011.
Project Update
Rovina Valley Project
Romania
Carpathian Gold announced its updated NI43-101 compliant mineral resource estimate (2012 Resource Estimate) as provided by AGP Mining Consultants which includes the Colnic, Rovina and Ciresata gold-rich copper porphyry deposits. All three deposits are in close proximity to one another and amenable to a central ore processing facility as described in the Preliminary Economic Assessment (PEA) completed in March 2010. Colnic and Rovina are amenable to open-pit mining and Ciresata to bulk underground mining. AGP has estimated the 2012 Resource Estimate for the RVP with a date cut off of April 23, 2012, updating the last resource estimate from November 2008 (2008 Resource Estimate) to include results from an additional 95 drill holes for 57,541 metres and utilized a total of 120,256 metres of diamond drill hole data from 251 drill holes.
AGP is pleased to announce their engagement by Roxgold to complete a Preliminary Economic Assessment (PEA) and a NI43-101 Compliant Technical Report for the Yaramoko Concession Project located in Burkina Faso.
Project Update
Yaramoko Concession
Burkina Faso
Roxgold Inc., Top Overall Company in TSX-V 50 for 2012, has engaged AGP Mining Consultants to prepare an initial resource on the 55 Zone of the Yaramoko property and prepare an updated Technical Report in compliance with NI43-101 Standards.
Project Update
Serra Pelada
Para, Brazil
Colossus Minerals announces significant achievement in metallurgical recoveries of platinum group metals from Serra Pelada, Brazil.
Team Update
PDAC 2012
Toronto, Canada
AGP Principals, Andy Holloway, Gordon Zurowski and Pierre Desautels will be in attendance at the PDAC Conference scheduled for March 4-7th, 2012. Please contact the office if you are unable to connect with them, and we will ensure your communications are forwarded.
Project Update
Bisha Mine
Eritrea
Principal, Jay Melnyk is pleased to have Bisha extended their contract with AGP to include Phase II Mine Planning and Mineral Reserves Update work.
Project Update
Hope Brook Project
Newfoundland, Canada
AGP is pleased to share in Castillian’s recent press release information and continues to offer Technical Services to Castillian as required.
Project Update
Ann Mason and Blue Hill Projects
Nevada, USA
After completion of various internal studies for Entrée Gold, the Company has retained the services of AGP to begin preparation of a Preliminary Economic Assessment for their Ann Mason and Blue Hill copper deposits. Re-assaying of portions of the historical Anaconda core, which will provide additional gold, silver and molybdenum data to support the upgraded resource estimate and PEA, is also underway. AGP looks forward to executing and completing this interesting study for this new client.
Project Update
Serra Pelada
Para, Brazil
AGP continues to provide project support to Colossus Minerals with AGP Principal Andy Holloway accepting a part-time position as the Colossus Consulting Metallurgist. Andy is working with DRA (Toronto) and P&K Engineers (Brazil) to design and construct the Serra Pelada Gravity Plant and also with Blue Coast Metallurgy to develop a PGM extraction process for this exciting project. See colossusminerals.com for site photographs and presentations.
Project Update
Serra Pelada
Brazil
AGP has been contracted by Colossus Minerals to provide metallurgical testwork supervision and process design/engineering services for the Serra Pelada Au-PGM project in Para State, Brazil.
Project Update
Rovina Valley Project
Romania
AGP is pleased to announce they will participate on the Pre-Feasibility Study for Carpathian Gold’s Rovina Valley Project. This will include geologic resource update, mine design (both open pit and underground), metallurgy and process design. In addition, AGP will be providing project management services together with Carpathian Gold’s management team in leading a multi-discipline team made up of specialist companies from various parts of the world working together with Carpathian Gold’s Romanian technical experts.
Project Update
Strieborna Project
Slovakia
AGP has been commissioned to review and assess all current technical inputs and reports by various 3rd parties for the Strieborna NI43-101 Preliminary Economic Assessment.
Project Update
Moss Property
Arizona, USA
Northern Vertex has signed a Technical Services Agreement with AGP to facilitate a review of current and historical drill programs and datasets.
Project Update
Tameapa Project
Sinaloa, Mexico
AGP has completed the NI43-101 Technical Report and PEA for MinCore’s Tameapa Project located in the front range of the Sierra Madre Mountains in Sinaloa State, Northwestern Mexico. The property hosts two mineral deposits; the Pico Prieto Copper-Molybdenum Porphyry and the Venado Molybdenum-Copper Breccia.
Project Update
Rovina Valley Project
Romania
AGP has been contracted to perform the geological services required to produce an NI43-101 compliant geological model and resource estimate update for the Rovina Valley Project.
Project Update
Nevsun Resources Ltd.
Nevsun has signed a Technical Services Agreement with AGP for assistance in evaluating mining properties and other technical support as required.
Project Update
Minago Property
Manitoba, Canada
AGP was excited to perform the geology model update for Victory Nickel, Minago Property. The results of the updated model are posted on Victory Nickel’s website
Team Update
PDAC 2011
Toronto, Canada
Andy Holloway, Gordon Zurowski and Pierre Desautels will be in attendance at the 2011 PDAC being held at The International Convention Centre in Toronto.
Project Update
Block A
Ontario, Canada
AGP was pleased to assist WGM with an Independent Mineral Resource Estimate and Technical Report for the M Zone and North Walter Lake zone, within the Block A Joint Venture property. The technical report, now uploaded onto the SEDAR website covers the Block A Property, incorporating the results of the 2010 drill program with revised economic parameters for the resource pit shell.
Project Update
Asmara Project
Eritrea
AGP is pleased to again be working with Sunridge Gold. Sunridge have commissioned AGP to prepare a metallurgical trade-off study designed to assist with scope definition for future engineering studies.
Project Update
Trade Wind Ventures
Ontario, Canada
In association with WGM, AGP continues to work with Trade Wind Ventures in expanding the resource base from the previous NI43-101. Pierre Desautels, Principal Geologist, for AGP Mining has been working together with Trade Wind staff on the update of his past work for them. An updated model is expected shortly.
Project Update
Tameapa Project
Sinaloa, Mexico
AGP is excited to commence work with MinCore by providing geological, metallurgical and mine engineering services to complete a Mineral Resource Estimate PEA of the Tameapa Project in Sinaloa, Mexico.
Project Update
Spanish Mountain Gold
British Columbia, Canada
The PEA for Spanish Mountain Gold Ltd. (SMG) is progressing toward completion. The proposed completion date is December, 2010.
Project Update
Santa Rita Mine
Bahia, Brazil
AGP’s Principal Process Engineer, Andy Holloway, will be working collaboratively with Dowding Reynard and Associates (DRA) to perform upgrade work on the Santa Rita Process Plant.
Project Update
NorthMet Project
Hoyt Lakes, Minnesota
AGP's technical staff has been providing support in the areas of mine planning, cost estimation and geology. This premier poly-metallic project is steadily advancing towards permit completion and construction.
Project Update
Malku Khota Project
Bolivia
AGP's technical staff has been retained to provide geological and engineering support to advance the Malku Khota project, a Silver and Indium resource located in Bolivia.
Project Update
Ghanzi Project
Botswana, Africa
AGP Mining technical staff has been assisting Hana Mining with the preparation of a Preliminary Economic Assessment (PEA) study for their Ghanzi project in Botswana. This exciting copper/silver property has a currently drilled strike length in excess of 60 kilometres with several areas potentially suitable for open pit mining. AGP's Michael Waldegger, P.Geo. recently visited the property in advance of his work preparing an updated NI43-101 resource together with Hana personnel. This resource will be used as the basis for the upcoming PEA study. AGP's geotechnical partner, BGC Engineering will be arriving on site mid-October to complete geotechnical investigations in support of that same study.
Project Update
Promontorio Property
Sonora, Mexico
The NI43-101 Resource was completed by AGP’s Michael Waldegger, P.Geo on September 28 and filed to SEDAR September 30th.